Triangles carry loads through pulling and pushing forces

A truss uses connected members mainly in tension, which pulls, and compression, which pushes. Triangles resist shape change without changing the members’ lengths.

More to Read

A pin-jointed rectangle can deform into a parallelogram, while adding a diagonal restrains that mechanism. Real joints are not perfect pins, but the comparison explains why triangulation is structurally useful.

Slide 2

The ideal model places loads at the joints

In an ideal truss, loads act at joints. Each member is a two-force element: it carries forces at its two ends, acting along its axis.

More to Read

A load applied between joints introduces bending into that member. The simple truss model is then incomplete unless the extra effect is included, showing why load placement matters as well as the outline.

Slide 3

Pushed members can buckle before they crush

Tension members resist being pulled apart. Compression members also need to resist buckling, which can occur before material crushing.

More to Read

A slender compression diagonal may require a larger section or bracing even when its axial force matches that of a tension member. Equal force does not imply identical design requirements.

Slide 4

Strong bars still need strong connections

Bolts, welds or other joints transfer forces between members. A truss with strong bars can still fail at a weak connection.

More to Read

Eccentric connections, where force lines do not meet at one point, create local bending. Actual joint geometry should therefore be reflected in analysis rather than replaced automatically by an ideal pin.

Slide 5

Extra depth can reduce force but needs more space

A deeper truss can reduce forces in its upper and lower members, called chords, for a given bending demand. It also occupies more space and changes bracing requirements.

More to Read

The upper and lower chords act as separated force paths forming a resisting couple. Increasing their separation can reduce the required force, but transport, clearance and construction constraints limit available depth.